EN 61000-4-5, “Electromagnetic compatibility (EMC) – Part 4-5: Testing and measurement techniques – Surge immunity test”, defines how to test the resistance of electrical equipment to high-energy voltage surges arriving on mains and signal lines. Laboratories simply call it the “surge test”; it is one of the basic immunity tests in EMC testing.
Let us take care of EN 61000-4-5 testing and the CE marking of your product together; CE Danışmanı (CE Consultant) manages the whole process.

What does this test simulate?
Lightning striking a building or nearby lines, and large loads being switched on and off, create very short but high-energy voltage surges on the mains. The surge test reproduces such a pulse in the laboratory and shows whether the equipment keeps working during the surge, or at least recovers by itself.
A surge is slower than an electrostatic discharge or a burst, but carries far more energy. The real load falls on the protection components (varistor, gas discharge tube, TVS diode) and the input stage.
EN 61000-4-5 at a glance
| Current edition | EN 61000-4-5:2014 (IEC 61000-4-5:2014) |
|---|---|
| Official title | Electromagnetic compatibility (EMC) – Part 4-5: Testing and measurement techniques – Surge immunity test |
| Type of standard | Basic EMC test standard: defines the test method; the level and the performance criterion are set by product and generic standards |
| Legislation | EMC Directive 2014/30/EU; harmonised product and generic standards refer to this test |
Which products does it apply to?
Almost every electrical and electronic product connected to the mains or to cables running outside the building: household appliances, IT and multimedia equipment (EN 55035), lighting, power supplies, drives, industrial control and measuring equipment.
- Double-insulated products without an earth connection are not tested line to earth.
- Isolated, filtered DC secondary circuits of 60 V or less are not tested.
- Long outdoor telecommunication lines use a separate waveform (10/700 µs).
Test setup

- Generator: the combination wave generator delivers a 1.2/50 µs voltage surge into an open circuit and an 8/20 µs current surge into a short circuit; its effective output impedance is 2 Ω.
- Coupling: the surge is injected into the power line through a coupling/decoupling network (CDN): 18 µF between lines, 10 Ω and 9 µF between line and earth.
- Decoupling: inductors in the CDN stop the surge from travelling back into the mains, so other equipment is not affected.
- Cable: the power cord between the equipment and the CDN is at most 2 m.
- Surges: on AC power ports, 5 positive and 5 negative surges at 0°, 90°, 180° and 270° for each coupling path; on DC and signal lines, 5 positive and 5 negative. At most 1 minute between surges.
- Levels: every level from the lowest up to the target level is applied in turn; a failure at an intermediate level is also recorded.
Test levels
| Level | Line to line | Line to earth |
|---|---|---|
| 1 | not applied | 0.5 kV |
| 2 | 0.5 kV | 1 kV |
| 3 | 1 kV | 2 kV |
| 4 | 2 kV | 4 kV |
| X | special level set by the product standard | |
For residential and industrial environments, most generic and product standards require 1 kV line to line and 2 kV line to earth on AC power ports; your product standard sets the exact level.
Performance criteria
- A: the equipment works normally within its specified limits, also during the surge.
- B: temporary degradation that recovers by itself. Most standards require this criterion for surge.
- C: temporary loss of function that needs user action or a restart.
- D: damage to hardware or software, or loss of data. The test is failed.
In every case the equipment must not become unsafe as a result of the test; this is assessed together with the Low Voltage Directive safety evaluation.
Place in the CE marking process
- The EMC standard of the product is identified; the surge level and criterion are read from it.
- Protection components and clearances on the board are reviewed during design; a pre-test is run if needed.
- The test is carried out in an accredited laboratory and a report is issued.
- The report goes into the technical file; the EU Declaration of Conformity under the EMC Directive is drawn up and the product is CE marked.
Standards applied together
- EN 61000-4-2: electrostatic discharge (ESD) immunity
- EN 61000-4-4: electrical fast transient (burst) immunity
- EN 61000-4-11: voltage dips and short interruptions
- EN 61000-6-1 and EN 61000-6-2: generic immunity for residential and industrial environments
Frequently asked questions
What is the difference between surge and burst?
Burst (EN 61000-4-4) is a train of very fast, low-energy pulses that imitates switching sparks. A surge is a single, slower pulse with much higher energy that imitates lightning and large load switching. A product can pass one and fail the other.
Which edition applies?
The current edition is EN 61000-4-5:2014. As a basic standard it is applied in the edition referred to by your product’s harmonised standard; check that reference before testing starts.
What if my product fails?
The input stage is usually strengthened: a varistor or gas discharge tube is added or resized, the fuse is matched to the protection component, clearances on the board are increased and the earth connection is shortened. The test is then repeated at the same level.
Other standards in this group
- EN 61000-4-3: Radiated RF Field Immunity Test
- EN 61000-4-4: Electrical Fast Transient Burst Test
- EN 61000-4-6: Conducted RF Immunity Test
- EN 61000-4-11: Voltage Dips and Interruptions Test
Our EMC test requirements tool shows which EMC tests your product needs in a few questions.