EN 61000-4-4, “Electromagnetic compatibility (EMC) – Part 4-4: Testing and measurement techniques – Electrical fast transient/burst immunity test”, defines how to test the resistance of equipment to trains of fast pulses on its power and signal lines. Laboratories call it the “burst test” or “EFT test”; it is one of the basic immunity tests in EMC testing.

Let us take care of EN 61000-4-4 testing and the CE marking of your product together; CE Danışmanı (CE Consultant) manages the whole process.

EN 61000-4-4 harmonised standard

What does this test simulate?

Opening a contactor or relay, stopping a motor or interrupting an inductive load puts very fast, short pulses onto the mains in rapid succession. The same pulses couple into signal cables running nearby. The burst test generates these pulse trains in the laboratory and shows whether the equipment keeps working.

The pulses carry little energy, but there are many of them and their edges are very steep; communication lines, sensor inputs and microcontroller reset circuits are the parts most affected.

EN 61000-4-4 at a glance

Current editionEN 61000-4-4:2012 (IEC 61000-4-4:2012, 3rd edition, replacing the 2004 edition)
Official titleElectromagnetic compatibility (EMC) – Part 4-4: Testing and measurement techniques – Electrical fast transient/burst immunity test
Type of standardBasic EMC test standard: defines the test method; the level and the performance criterion are set by product and generic standards
LegislationEMC Directive 2014/30/EU; harmonised product and generic standards refer to this test

Which products does it apply to?

Almost every electrical and electronic product connected to the mains or fitted with external cables: household appliances, IT and multimedia equipment (EN 55035), lighting, power supplies, motor drives, PLCs and control panels, measuring instruments.

  • Power ports, the protective earth (PE) port and signal/control ports are tested separately.
  • The generic standards test signal lines only where the cable may be longer than 3 m.
  • Battery-powered equipment without external cables has no port left to test.

Test setup

EN 61000-4-4 burst test setup (schematic)

  1. Generator: the EFT/B generator produces pulses with a 5 ns rise time and 50 ns width. They arrive in 15 ms bursts (0.75 ms at 100 kHz) at a repetition frequency of 5 kHz or 100 kHz; the bursts repeat every 300 ms.
  2. Power ports: the pulses are injected into the power line through a coupling/decoupling network (CDN) with 33 nF coupling capacitors; the decoupling section keeps them out of the mains.
  3. Signal lines: no direct connection is made; the cable is laid inside a capacitive clamp and the pulses are coupled onto it through the clamp.
  4. Ground: the equipment stands on a 0.1 m insulating support above a ground reference plane (GRP) of at least 0.8 × 1 m; the GRP extends at least 0.1 m beyond the equipment on all sides and is connected to protective earth. Cables are kept 0.1 m above the GRP.
  5. Distance: 0.5 m between the coupling device and table-top equipment, 1 m for floor-standing equipment; excess cable is bundled.
  6. Application: both polarities are applied to each port, long enough to exercise all operating modes and never less than 1 minute; ports are tested in turn.

Test levels

LevelPower and PE ports (peak)Signal and control ports (peak)
10.5 kV0.25 kV
21 kV0.5 kV
32 kV1 kV
44 kV2 kV
Xspecial level set by the product standard

The generic standards require ±1 kV on AC power ports in residential environments and ±2 kV in industrial environments; on signal lines ±0.5 kV and ±1 kV with the clamp. A repetition frequency of 5 kHz is traditional, 100 kHz is closer to real mains events; the product standard says which one applies.

Performance criteria

  • A: the equipment works normally within its specified limits, also during the bursts.
  • B: temporary degradation that recovers by itself. The generic standards require this criterion for burst.
  • C: temporary loss of function that needs user action or a restart.
  • D: damage to hardware or software, or loss of data. The test is failed.

In every case the equipment must not become unsafe as a result of the test; this is assessed together with the Low Voltage Directive safety evaluation.

Place in the CE marking process

  1. The EMC standard of the product is identified; the burst level, the repetition frequency and the criterion are read from it.
  2. Input filters, the chassis bonding of cable screens and common-mode chokes on signal lines are reviewed during design; a pre-test is run if needed.
  3. The test is carried out in an accredited laboratory; the report records the ports, the coupling method and the test duration.
  4. The report goes into the technical file; the EU Declaration of Conformity under the EMC Directive is drawn up and the product is CE marked.

Standards applied together

Frequently asked questions

What is the difference between burst and surge?

Burst is a train of very fast, low-energy pulses in the nanosecond range that imitates relay and contactor switching. Surge (EN 61000-4-5) is a single, slower pulse in the microsecond range with far more energy that imitates lightning. The protection components and the failure modes differ; a product can pass one and fail the other.

5 kHz or 100 kHz?

The standard defines both. 5 kHz has been used for a long time; 100 kHz is closer to real switching events. The product standard may require one or both; the generic standards allow either.

What if my product fails?

Ferrites or common-mode chokes are usually added to the lines, cable screens are bonded to the chassis over 360°, RC filters are placed on signal inputs, and the firmware watchdog and communication error recovery are strengthened. The test is then repeated on the same ports.

Other standards in this group

All standard guides

Our EMC test requirements tool shows which EMC tests your product needs in a few questions.

Get an offer for your product

Scope, timeline and price in three steps.

  1. 1Tell us about your productAttach a datasheet or photos if you have them
  2. 2Scope and tests become clearDirectives, tests, notified body
  3. 3Price and timeline in your handsOffer within one business day

Prefer to talk now?

Leave your details

Reply within one business day

By sending this form you agree that your data is processed as described in our Privacy & Cookie Policy.